The Development of Moorend Golf Course is being carried out
in stages and will approximately take three or four years
from he 1/1/2002. These stages include building both facilities
and improvements to the course.
|
Key Stages
1) The building of a club house/tarmacing of the car
park -
The facilities provided will be toilets, showers, lockers
a cafe, a new Golf shop and much more..
2) Finishing off the new 3rd, 4th & 7th greens
3) Repair and Enlargement of existing raised tees
4) Comprehensive drainage of course and driving range
- each winter drainage will be improving expected finish
date 2005.
|
 |
5) Excavation of the 9th pond and building of 9th tee and
green - Expected finish date september 2004.
6) The finishing of the new tees
7) Finally once the tees and greens are finished and fairway
drained. All fairway bunkers will be enlarged and more created,
expected completion date september 2005.
Staring in 1996 we have been constantly developing the course
and facilities at Moorend Golf Course.
|